Extension of Time Claims: What a Properly Supported EOT Submission Contains

An extension of time claim is a request to move the date for practical completion because of a delay the contract allows time for. It changes the date, and it does not automatically carry money with it. Cost entitlement is assessed separately, under different provisions and against a different test. 

This article sets out what a properly supported EOT submission contains, how delay is analysed and what a principal or superintendent looks for when assessing one, with a focus on Australian civil infrastructure and resources projects. It is written for both sides of the table, because the evidence that makes a claim defensible is the same evidence that lets a principal assess it fairly. 

What an extension of time claim is, and what it is not 

An EOT moves the contractual date for completion. Its practical effect for the contractor is relief from liquidated damages for the period granted. 

Whether the contractor is also entitled to delay costs is a separate question. A contractor can be granted time with no money, which is the normal outcome where the delay was neutral rather than caused by the principal. 

Causes that commonly qualify include: 

  • Variations and directed changes to scope 
  • Late issue of drawings, information or approvals 
  • Late or restricted access to work areas 
  • Latent or unforeseen site conditions 
  • Suspension directed by the superintendent 
  • Acts or omissions of the principal or of other contractors engaged by the principal 
  • Any further qualifying cause named in the contract 

The contract decides. In standard Australian contract forms, the qualifying causes and the claim process sit within the time provisions, and amended special conditions frequently narrow them. 

Notice obligations usually decide the claim before the analysis starts 

Most EOT claims that fail do not fail on the delay analysis. They fail on notice. 

Contracts routinely set a short window for notifying a delay event, often within a set number of days of the contractor becoming aware of it, with a more detailed claim to follow. Where that notice is drafted as a condition precedent, missing it can extinguish the entitlement no matter how well founded the delay was. 

Three things are worth confirming before any analysis work begins: 

  • Whether notice was given in the form and within the period the contract requires 
  • Whether the contract makes that notice a condition precedent to entitlement 
  • Whether the contract gives the superintendent any separate power to extend time 

Contractors should treat notices as administrative routine rather than as a decision to be weighed each time. Principals should expect to receive them and should not read a notice as an escalation. 

The records that carry a claim 

Delay is proved with contemporaneous records, meaning records created at the time rather than assembled afterwards. A submission built from a retrospective narrative gets discounted, and usually should be. 

The records that do the work are: 

  • The contract baseline program as accepted, together with its basis of schedule 
  • Every program update in the period, with the data date and progress as recorded at the time 
  • Daily site diaries and labour, plant and weather returns 
  • Correspondence, including the notices themselves and any direction from the superintendent 
  • Progress meeting minutes, where the delay was raised at the time 
  • Variation records, requests for information and the dates they were answered 
  • Dated photographs and survey or quantity records 
  • Access, possession and road occupancy approvals, with the dates they were requested and granted 

Records only hold value if they are kept consistently. A project where diaries are completed in some weeks and not in others gives an assessor a reason to discount the whole set. On multi-package projects, a well-kept interface register helps here, because it records when each handover was required and when it actually happened. 

Choosing a delay analysis method 

The method should follow the records available, the contract requirements and the timing of the assessment, not the other way around. The Society of Construction Law Delay and Disruption Protocol is a widely used reference that describes the common techniques. 

Impacted as-planned. Delay events are inserted into the baseline program. Quick and cheap, and widely criticised because it ignores what actually happened on site. Used mainly for early, low value claims. 

Time impact analysis. The delay event is modelled into the program update current at the time it occurred. Prospective in nature and well suited to contemporaneous assessment during the works. It depends on reliable, regular updates. 

As-planned versus as-built windows. The program is split into windows and progress in each window is compared against plan. Retrospective, record heavy, and generally the most persuasive where the records support it. 

Collapsed as-built. Delay events are removed from the as-built program to show what would have happened without them. It depends on a reliable as-built and a defensible logic set. 

None of these works without a credible baseline. If the baseline carries open ends, hard constraints holding dates in place, or durations with no quantity basis, the analysis built on top of it will not hold up under review. 

Concurrent delay and who owns the float 

Concurrency is where most EOT disputes end up. Where a principal caused delay and a contractor caused delay overlap in the same period and both affect the critical path, the usual Australian starting position is that the contractor may be entitled to time but not to delay costs for that period. The outcome turns heavily on the drafting, and some contracts deal with concurrency expressly. 

Float ownership should be settled early as well. Where the contract is silent, the common position is that float belongs to the project rather than to either party and is consumed by whichever event uses it first. Contracts that say otherwise need to be read carefully, because this single point can change the result of an entire claim. 

How a principal assesses an EOT submission 

From the other side of the table, assessment usually runs in sequence: 

  • Was notice given in time and in the required form 
  • Is the cause one the contract recognises 
  • Is the baseline being used the program the parties actually accepted 
  • Does the analysis rely on contemporaneous records, or has it been built backwards from the outcome 
  • Does the delay sit on the critical path to completion, and can that be demonstrated in the program 
  • Is there concurrent contractor delay in the same window 
  • Is the period claimed supported by the analysis, or has it been rounded up 

A submission that answers these in order and shows its working gets assessed faster, and more often in part. A submission that arrives as a narrative with a bar chart attached generally does not. 

Prolongation cost is assessed separately 

Where delay costs are claimed, they are assessed against the period of delay actually granted and against costs actually incurred, usually time-related site overheads rather than a rate carried through from the tender. Off-site overhead and profit claims are treated cautiously and often need specific contractual support. 

Keeping cost records aligned to the delay period from the start is far easier than reconstructing them once the claim is on foot. 

How Consilium supports extension of time claims 

Consilium supports extension of time claims as part of an integrated project controls team, working on both sides of these submissions: preparing claims for contractors and assessing them for principals and superintendents. The work normally covers baseline review, forensic program analysis, records assembly, method selection and the written delay narrative that ties the evidence to the program. 

Because the same team builds and maintains the programs, cost reports and records that a claim relies on, the evidence is in place before a delay occurs rather than reconstructed after it. The team uses Primavera P6 for scheduling, Safran Risk for quantitative schedule risk analysis, Synchro 4D for sequencing and Power BI for reporting. Project Controls Services sets out the full scope. 

Talk to Consilium about a delay or a claim 

For support with an extension of time claim, a baseline review or forensic program analysis, or for an integrated project controls team that keeps your program and records claim-ready from the start, see Project Controls Services or Project Management Services, or contact the team to discuss the project. 

Disclaimer. This article is general information about project controls and delay management practice. It is not legal advice. Entitlement under any contract depends on the terms of that contract and the facts of the project, and specific claims should be assessed with appropriate legal and commercial advice. 

Frequently Asked Questions 

What is an extension of time claim? 

An extension of time claim is a request to move the contractual date for practical completion because of a delay the contract allows time for. Granting it relieves the contractor of liquidated damages for the period granted. 

Does an extension of time also mean extra payment? 

Not automatically. Time and cost are assessed under separate provisions. A contractor can be granted an extension of time with no entitlement to delay costs, which is the normal outcome where the delay was neutral rather than caused by the principal. 

What records support an extension of time claim? 

The accepted baseline program, the program updates current at the time of the delay, site diaries, correspondence and notices, progress meeting minutes, variation and request for information records, and dated photographs. Records created at the time carry far more weight than material assembled afterwards. 

Which delay analysis method should be used? 

The method should follow the records available, the contract requirements and the timing of the assessment. Time impact analysis suits contemporaneous assessment during the works, while as-planned versus as-built windows analysis is generally more persuasive where complete records exist. 

What is concurrent delay? 

Concurrent delay is where a delay caused by the principal and a delay caused by the contractor overlap in the same period and both affect the critical path. The usual starting position in Australia is that the contractor may receive time but not delay costs for that period, subject to what the contract says. 

What does EOT support from a project controls team involve? 

It is a service rather than a software product. It typically covers baseline review, forensic program analysis, assembling contemporaneous records, selecting an appropriate delay analysis method, and preparing or assessing the written delay narrative. It works best when the same team also maintains the program and records during delivery. 